PROJECT

Projects

Environmental & Social Review Summary

Project Number

25151

Company Name

Tanzania Railway Corporation

Date ESRS Disclosed

Jun 22, 2007

Country

Tanzania

Region

Africa

Last Updated Date

Nov 30, 2016

Environmental Category

B - Limited

Status

Completed

Previous Events

Approved : Jul 26, 2007
Signed : Sep 15, 2007
Invested : Jun 11, 2008

Sector

Rail Transportation

Industry

Infrastructure

Department

Gbl Infrastructure & Natural Resources

Project Description

IFC''s loan will support the rehabilitation and development of the former TRC system in Tanzania. The railway in Tanzania has historically served as a vital lifeline for a large population in Tanzania and its landlocked neighboring countries. Tanzania has two railway systems, the Tanzania Railway Corporation (TRC) and the Tanzania Zambia Railway (TAZARA). TRC operates on the Central Transport Corridor (CTC), connecting the Port of Dar Es-Salam (DSM) with major urban centers and inland rural areas and serving the central and northern parts of the country as well as transit traffic from the eastern side of the Democratic Republic of Congo (DRC), Burundi, Rwanda, Uganda (the CBRU Countries). TAZARA originates from the outskirts of DSM and principally serves Zambian traffic and some domestic traffic in Southern Tanzania on the Southern Transport Corridor (STC). In addition to these two operators, there is a third operator called Trans Africa Railway Corporation (TARC) which track access rights to operate international transit traffic originating from Southern Africa and transshipped at KIDATU from TAZARA to TRC railway networks, TARC has not moved any transshipment cargo in the year 2006.

TRL’s rehabilitation and development program will be executed in five, five-year phases over the life of the concession. The first phase, to be partially funded by IFC, will include:


- the rehabilitation of fixed infrastructure including primary and secondary track renewals, ballasting, bridge rehabilitation, and signaling and telecommunication upgrading,
- purchasing of track maintenance equipment and trolleys,
- capital repairs of rolling stock, and
- initial working capital requirements.

Overview of IFC's Scope of Review

The rehabilitation, development, and operation of the approximately 2,700 route-km Tanzania Railways Corporation (TRC) network currently operated by TRC, a parastatal enterprise of the Government of Tanzania (GOT), is being concessioned to a special purpose company, Tanzania Railways Limited (TRL), set up by a consortium led by RITES Limited of India (RITES or the Concessionaire), selected through an international competitive tender process.

RITES is a public limited company under the Ministry of Railways, Government of India, and has experience in over 62 countries, including railway operations experience in Africa for over 25 years. The objective of the concession is to improve the management, operation and financial performance of the rail network by granting exclusive rights to TRL for the provision of freight and passenger services and operation and maintenance of the concession assets for the duration of the concession. The 25-year concession was awarded in March 2006 and formal handover of the operations is expected following closing of financing. It is proposed to extend an IFC project finance loan to TRL to support its first five year investment program.

IFC’s Environmental and Social review of this project focused on the social, labor, and environmental components of the project that will be the responsibility of the private operator from the date the Concession is formally handed over. The Concession provides that all pre-existing environmental and social liabilities will remain the responsibility of the conceding authority, while the Concessionaire would take over operation and maintenance of the railway. The World Bank supported the concession process as part of the Central Transport Corridor Project and other initiatives. More specifically, the World Bank’s engagement in this process includes:

- Funding of rails, sleepers, and related materials for the renewal of :


(a) 158 km of mainline track between Itigi and Tabora and
(b) other priority sections as identified by the Concessionaire;

- Preparation of Environmental and Social Assessments for the Itigi to Tabora renewal project, and an Environmental Management Plan and a Resettlement Action Plan for the TRC system;
- Financing of cleanup and resettlement costs based on the above studies; and
- Technical advisory services and training to TRC to facilitate the handover process.

The GOT is taking responsibility for the retrenchment of staff not needed by the concessionaire, and past environmental and social liabilities.

IFC is relying on support by the World Bank to ensure that its Safeguard Policies are met related to retrenchment and other social mitigation of railway staff, as well as the relocation of people and businesses that have encroached on the rights-of-way as required to provide a safe corridor for railway traffic. As the GOT is responsible for mitigation of environmental shortcomings, IFC’s review also considered the capacity of RITES to support the GOT in these matters and to achieve environmental compliance in a reasonable timetable.

IFC examined the following key documentation as part of its review:

- Project Appraisal Document for an International Development Association credit to the United Republic of Tanzania for the Central Transport Corridor Project, March 31, 2004
- Request for Technical and Financial Proposals, Tanzania Railways Corporation Concession, Volume 2: Information Memorandum, June 2004
- Gibb Eastern Africa, Environmental Audit for the Tanzania Railway Corporation
- SMEC International Pty Ltd, Environmental Impact Assessment, Central Transport Corridor Project, Railway Rehabilitation Project – Itigi to Tabora, prepared for Tanzania Railways Corporation, April 2005
- Scott Wilson, Resettlement Action Plan, prepared for Tanzania Railways Corporation, April 2007
- RITES Limited, Feasibility Report for the Tanzania Railways Corporation Concession, May 2007
- CANAC INC., Draft Report – Technical Audit Study for the Tanzania Railway Concession, prepared for IFC, June 14, 2007

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement