PROJECT

Projects

Environmental & Social Review Summary

Project Number

24711

Company Name

THE WEST COAST PAPER MILLS LIMITED

Date ESRS Disclosed

Feb 5, 2007

Country

India

Region

South Asia

Last Updated Date

Jun 3, 2021

Environmental Category

B - Limited

Status

Completed

Previous Events

Approved : Jun 6, 2007
Signed : Jun 28, 2007
Invested : Mar 31, 2008

Sector

Paper for Printing and Writing

Industry

Agribusiness and Forestry

Department

Regional Industry - MAS Asia & Pac

Project Description

The West Coast Paper Mills Ltd., (WCPM or the company) is undertaking a modernization and expansion project consisting of:

- installation of new pulp mill facility of 246,500 tons per annum (tpa) and shutdown of the old pulp mill;
- installation of a new writing/printing paper machine with capacity of 135,000 tpa;
- upgrade of its existing duplex board machines to improve quality and increase production by about 6,500 tpa; and
- installation of additional equipment for effluent treatment, chemical recovery and power plants to improve environmental performance and reduce costs.

The project will be implemented over a three years period and will allow the company to enhance its competitiveness by reducing costs due to:

- achieved economies of scale as a result of the capacity increase;
- strengthened input/output ratio as a result of the new technology; and
- a switch from inefficient stoker-fired boilers to fluidized bed combustion (FBC) boilers.

It will also enable WCPM to widen its product range and increase the proportion of value-added products. The company has requested the Government of Karnataka for an allotment of 50,000 hectares (ha) of land in adjoining districts under a Design, Build, Finance, Operate, Maintain and Transfer (DBFOMT) scheme for taking up captive plantations. This will give an additional impetus to the availability of raw material locally, thereby eliminating procurement of raw material from other states or through imports. This effort would also bring down the average distance of raw material procurement from the present 700kms to 200kms. The company has also embarked on a program wherein 18,000 hectares of unproductive agricultural land within a 250km radius of Dandeli will be developed as managed plantations of pulpwood trees such as eucalyptus, casuarina, acacia and subabul in the next five years, which is expected to yield some 250,000 metric tons of pulpwood per annum from the year 2011 onwards. The material will be of uniform size and superior quality.

Overview of IFC's Scope of Review

The review of this project consisted of appraising technical, environmental and social information submitted by the project sponsor including a review of the following documents:

- Industrial Safety Committees for WCPM Plants 2006-2007;
- Listing of WCPM Industrial Safety Crisis Group Members (Local and District Level) for 2006-2007;
- Statistical Analysis of Accident and approximate Loss to Organisation for October and November 2006;
- Central Laboratory Results of the Joint samples taken by KSPCB from Jan 2006 to Nov. 2006;
- Karnataka State Pollution Control Board Consent dated 17th July 2006;
- Schematic of Central Laboratory Effluent Treatment Plant and Sampling Points;
- Stakeholder responsibility report (2005);
- Monthly WCPM Air pollution monitoring report submitted to KPCB December 2006;
- Karnataka State Pollution Control Board Report dated 08/10/2006;
- Safety Work Permit – sample;
- WCPM Tripartite labor agreement for 2003-2006;
- On site and Off site Emergency Master Plan dated Sept. 2005;
- REIA for WCPM Project Expansion and Modernization dated May 2006;
- Executive Summary of REIA translated into Kannada for public hearing on REIA;
- Current enrolment (2006) at all Dandeli educational institutions funded by WCPM;
- Statutory Compliance Letter to Company Secretary dated 10/01/2007; and
- 2005-06 Community development initiatives undertaken by WCPM for nearby villages.

In addition, the appraisal team visited the existing plant in Dandeli and held discussions with WCPM’s senior management team.

The following potential environment, health and safety and social aspect of the project were analyzed:

- social, environmental, and health and safety management systems;
- government clearance and permitting process;
- management of construction impacts;
- fair, healthy and safe working conditions during construction and operation;
- hazardous materials management;
- air and noise emissions and ambient air quality;
- minimization, treatment and disposal of liquid, solid and hazardous wastes;
- occupational health, safety, hygiene, and emergency response planning; community health, safety, security and engagement; and
- corporate social responsibility and community development programs.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Client Documentation

File Name Actions
WCPM FINAL ESAP dated 5 Feb 2007.pdf