Project Number

24373

Company Name

IPR TRANSOIL CORPORATION

Date ESRS Disclosed

Nov 28, 2006

Country

Egypt, Arab Republic of

Region

Africa

Last Updated Date

Sep 30, 2022

Environmental Category

B - Limited

Status

Completed

Previous Events

Approved : Feb 16, 2007
Signed : Jun 6, 2007
Invested : Aug 7, 2007

Sector

Oil and Gas Production (Includes Development)

Industry

Metals and Mining

Department

Gbl Infrastructure & Natural Resources

Project Description

The IPR Group of Companies (IPR or the company) is a group of privately-held domestic and international companies that engages in exploration and production of oil primarily in Egypt, but also elsewhere in Syria and Pakistan. IPR is headquartered in Dallas, Texas, where, besides being active in exploration and production through its affiliates in Egypt, Pakistan and Syria, it also provides petroleum consulting services through out the world. IPR’s existing production is largely concentrated in its Alamein Yidma concession in the Western Desert area of Egypt, but it also has existing production in the Gulf of Suez from the North July concession. IFC has been asked to provide financing of up to $25 million to help fund a portion of IPR’s capital expenditure program for the 2006-2009 period. The program (drilling nine new wells and undertaking 51 well interventions or workovers, plus auxiliary facilities) will focus primarily on the further appraisal and development of its Almein Yidma field, but will also target exploration and development of five other oil fields in Egypt, namely, North Bahariya,North Ras Qatara and El Diyur all located in the Western Desert, and the Southwest Gebel El Zeit, North July and North Ramadan fields offshore in the Gulf of Suez.

Overview of IFC's Scope of Review

The IFC Environment and Social specialist visited the project site(s) in September 2005, in addition, the project review included the review of environmental and social information. The following corporate systems and potential environment, health, safety and social impacts of the project were analyzed: - Establishment of an integrated Environmental, Health, Safety and Social (EHSS) Management System at the corporate level, as well as specific system in Egypt; - The company’s capacity to manage multiple projects and implement the Integrated Management System; - Impacts from construction; - Liquid and solid waste disposal; - Public and worker safety; - Emergency and response plans; - Land acquisition and compensation process; - Community relations including consultation and disclosure; - Cultural resources management and chance find procedures; and - Community development.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Client Documentation

File Name Actions
Corrective Action Plan-IPR.pdf