PROJECT

Projects

Environmental Review Summary

Project Number

23237

Company Name

Obajana Cement PLC

Date ERS Disclosed

Jan 28, 2005

Country

Nigeria

Region

Africa

Date Revised ERS Disclosed

Apr 21, 2005

Environmental Category

A - Significant

Status

Completed

Previous Events

Approved : May 5, 2005
Signed : Jun 16, 2005
Invested : Mar 1, 2006

Sector

Gas - Thermal Power Generation

Industry

other

Department

Regional Industry - MAS Africa

Project Description

The Obajana Cement Project (OCP) involves the construction and operation of a greenfield cement plant at Obajana, Kogi State, 220 km southwest of Abuja, the Nigerian capital. The project will have a combined production capacity of 4.4 million metric tonnes per annum (mtpa) and includes a 135 MW captive gas power plant; a 94 km gas pipeline; a limestone quarry with associated 7.5 km conveyor belt; a 13m high dam impounding a reservoir with a total storage capacity of 5.1 million m3 and a 328 unit housing complex for non-local staff. The estimated project cost is $798 million, to be financed with sponsor''s equity of $319 million (40% of the Project''s capitalization) and $479million in form of long-term debt from local and international lenders. The Sponsor is Dangote Industries Ltd (“DIL”), a leading Nigerian manufacturing and trading company. The project represents their first venture into cement production. Project implementation started in 2003 and commissioning is expected in 2005.

Environmental and Social

Availability of Full Documentation

Environmental and Social Documentation

File Name Actions
Obajana Cement Resettlement Audit.pdf
Obajana Executive Summary.pdf
Objana EHSS Action Plan.pdf