Approved : Jun 28, 2005 Signed : Jun 30, 2005 Invested : Feb 14, 2007
Sector
Aluminum
Industry
other
Department
Gbl Ind, Manufact, Agribus & Services
Project Description
Assan Demir ve Sac Sanayii A.S. (Assan), part of the Kibar Group, is the largest player in the Turkish aluminum sheet, coil, and foil industry, and also ranks amongst the top Turkish steel galvanizing companies. This $125 million project comprises restructuring of the company’s balance sheet and implementing a $25 million debottlenecking and modernization program, primarily at their aluminum plant.
Environmental and Social
IFC requires that this document is made available through the World Bank InfoShop and to the locally affected community no less than 30 days prior to project consideration by the IFC Board of Directors. The Summary of Project Information (SPI) also provides details of where the ERS has been made available to the locally affected community. The SPI must also be sent to the World Bank InfoShop no less than 30 days prior to project consideration by the IFC Board of Directors.
This is a Category B project according to IFC’s Procedure for Environmental and Social Review of Projects because a limited number of specific environmental impacts may result which can be avoided or mitigated by adhering to generally recognized performance standards, guidelines or design criteria. The review of this project consisted of appraising technical and environmental information submitted by the project sponsor as well as visits to the aluminum and galvanizing plants. The potential environment, health and safety (EHS) impacts of the project were analyzed related to the compliance of the aluminum plant with Turkish and IFC EHS requirements.
Assan has presented plans to address these impacts to ensure that the proposed project will comply with the environment, health and safety (EHS) requirements of Turkey as well as IFC’s environment and social policies and the environmental, health and safety guidelines. Information about how these potential impacts will be addressed by Assan is summarized in the paragraphs that follow.
As a result of earlier IFC investments in Assan’s aluminum plant in Tuzla, the company had prepared a very detailed annual monitoring report of this operation. The report was prepared by the Department of Environmental Engineering at Istanbul Technical University. The report provides extensive monitoring data for air emissions, liquid effluents, solid wastes, noise as well as indoor air quality and indoor noise levels. The report provides third-party verification that the aluminum plant fully complies with all relevant Turkish requirements in this regard (both local and central government) as well as with applicable IFC environmental, worker health and safety (EHS) and social requirements.
At the end of CY2003 Assan’s aluminum plant has successfully completed the transition to ISO 9001:2000 (Quality Management) and achieved TS 18001 in compliance with OHSAS (Occupational Health and Safety) standards. Additionally Assan’s aluminum plant is currently in progress to completing the application requirements for ISO 14001 (Environmental Management). This is yet another indication of Assan’s commitment to quality, performance, worker health and safety and outstanding environmental performance.
The proposed project includes further investments in equipment to improve on the already very high product quality, to further improve worker health and safety; and to also improve the company’s outstanding environmental performance.
This ERS contains the full environmental and social documentation prepared for the project.
Conclusion & Monitoring
Accordingly, IFC concludes that the proposed project meets the applicable IFC environment and social policies and the environmental, health and safety guidelines as well as relevant Turkish requirements.
IFC will evaluate the project's compliance with the applicable Turkish and IFC environmental, health and safety (EHS) and social requirements during the lifetime of the project by reviewing the annual monitoring reports (AMRs) prepared for the project by the company covering the ongoing performance of project-specific environmental, health and safety (EHS) activities. Periodic site supervision visits will also be conducted.
Press-Release
Related SPI
Similar Projects
This Environmental Review Summary (ERS) is prepared and distributed in advance of the IFC Board of Directors' consideration of the proposed transaction. Its purpose is to enhance the transparency of IFC’s activities, and this document should not be construed as presuming the outcome of the Board of Director’s decision. Any documentation that is attached to this ERS has been prepared by the project sponsor or in conjunction with the project sponsor and authorization has been given for public release. IFC has reviewed this documentation and considers that it is of adequate quality to be released to the public but does not endorse the content. The following ERS is disclosed in accordance with IFC's Disclosure of Information Policy that went into effect September 1998.
The map is for illustrative purposes and does not imply the expression of any opinion on the part of the World Bank, concerning the legal status of any country or territory or concerning the delimitation of frontiers or boundaries. Country borders or names do not necessarily reflect the World Bank Group's official position. In some cases, available project location information is limited to the country of the project's activities. Locations are approximate.