Mira Power Limited (“MPL” or the “Company”), a special purpose vehicle, was formed to undertake the construction, operation and maintenance of a 100MW run-of-the-river hydro power plant under a Build-Own-Operate-Transfer scheme (the “Project”). Located 167 km east of Islamabad, the Project components are situated 5 km south of Kotli Town on the Poonch River and its confluence with the Bann Nullah River. The Project will sell all of its electricity to the National Transmission and Dispatch Company of Pakistan under a 30-year Power Purchase Agreement. The Project cost is approximately US$344 million.
Below is the link to the Environmental and Social Impact Assessment (ESIA) and Environmental and Social Management and Monitoring Plan (ESMMP) prepared by third parties.